Formation of EEL

2010

Subcontract Received

1st major HDD sub-contract in Indonesia

(20” X 1900M)

2011

Acquired

The entire equipment fleet of Stroytrangaz* in India

2012

Acquired

Largest capacity HDD rig in India

- Prime Drilling PD500 (500T)

rig

2013

Subcontract Received

In Nigeria worth USD 35 Mn.

(18”, 94KM)
 

HDD crossing for ISPRL, India

(48+” 702M)

2015

Projects Completed

2KM Ganga River HDD Crossing (One of India’s longest at the time)
Installation of 16’’ OD Pipeline (Panam River)

2016-17

Subcontract Received

16” Pipeline in KA

from TJTC (for IOCL)

2019

Projects Awarded and Completed

Completed:

A fast track 36” 95KM Balance Pipeline works (DAPL project – GAIL)
 

Awarded:

141Km 26”

Pipeline project from NRL (02-2023)